Analyze construction schedule delays for claims and recovery. Perform time impact analysis, identify delay causes, calculate damages, and document for disputes.

190estrelas
Atualizado há 8 meses

Ver no GitHub ↗ Licença: MIT

Como adicionar

/plugin marketplace add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction

O comando exato pode variar conforme o repositório. Confira o README no GitHub.

Para o autor da skill

Cole no README do seu repo

Mostra que sua skill está catalogada na Skillteca, gera backlink e tráfego rastreável.

[![Skillteca](https://www.skillteca.com.br/api/badge/delay-analysis/svg)](https://www.skillteca.com.br/skills/delay-analysis)
#ai

Skills relacionadas

Ver todas de Documentos →

Alerta por categoria

Receba novas skills de Documentos toda segunda

1 email curto, só com as skills novas de Documentos. 4 minutos de leitura, sem spam, cancela com 1 clique.

Você confirma o email no primeiro envio. Sem spam. Cancela com 1 clique.

Ler descrição completa

Delay Analysis

Overview

Analyze construction schedule delays for project recovery and claims. Perform time impact analysis (TIA), identify concurrent delays, calculate delay damages, and prepare documentation for dispute resolution.

"Proper delay analysis is essential for fair resolution of construction disputes" — DDC Community

Delay Analysis Methods

┌─────────────────────────────────────────────────────────────────┐
│                    DELAY ANALYSIS METHODS                        │
├─────────────────────────────────────────────────────────────────┤
│                                                                  │
│  As-Planned vs As-Built    │    Time Impact Analysis (TIA)      │
│  ─────────────────────     │    ────────────────────────────    │
│  Compare original to       │    Insert delay events into        │
│  actual schedule           │    schedule to measure impact      │
│                            │                                     │
│  Windows Analysis          │    Collapsed As-Built              │
│  ────────────────          │    ─────────────────               │
│  Divide project into       │    Remove delays from as-built     │
│  time periods              │    to find "but-for" completion    │
│                                                                  │
└─────────────────────────────────────────────────────────────────┘

Technical Implementation

from dataclasses import dataclass, field
from typing import List, Dict, Optional, Tuple
from datetime import datetime, timedelta
from enum import Enum
from collections import defaultdict

class DelayType(Enum):
    EXCUSABLE_COMPENSABLE = "excusable_compensable"      # Owner caused - time + money
    EXCUSABLE_NON_COMPENSABLE = "excusable_non_compensable"  # Neither party - time only
    NON_EXCUSABLE = "non_excusable"                      # Contractor caused - no relief
    CONCURRENT = "concurrent"                            # Both parties - complex

class DelayCause(Enum):
    OWNER_CHANGE = "owner_change"
    LATE_INFORMATION = "late_information"
    DIFFERING_CONDITIONS = "differing_conditions"
    PERMIT_DELAY = "permit_delay"
    WEATHER = "weather"
    LABOR_SHORTAGE = "labor_shortage"
    MATERIAL_DELAY = "material_delay"
    SUBCONTRACTOR = "subcontractor"
    COORDINATION = "coordination"
    ACCESS = "access"
    FORCE_MAJEURE = "force_majeure"

@dataclass
class DelayEvent:
    id: str
    description: str
    cause: DelayCause
    delay_type: DelayType
    start_date: datetime
    end_date: datetime
    affected_activities: List[str]
    responsible_party: str
    documented: bool = True
    supporting_docs: List[str] = field(default_factory=list)
    calculated_impact: int = 0  # days
    concurrent_with: List[str] = field(default_factory=list)

@dataclass
class ScheduleVersion:
    version_id: str
    version_type: str  # baseline, update, as-built
    data_date: datetime
    completion_date: datetime
    activities: Dict[str, Dict]  # activity_id -> {start, finish, duration}

@dataclass
class WindowPeriod:
    window_id: str
    start_date: datetime
    end_date: datetime
    planned_progress: float
    actual_progress: float
    delay_days: int
    delay_events: List[str]
    responsible_parties: Dict[str, int]  # party -> delay days

@dataclass
class DelayAnalysisReport:
    project_name: str
    analysis_date: datetime
    original_completion: datetime
    actual_completion: datetime
    total_delay: int
    excusable_delay: int
    non_excusable_delay: int
    concurrent_delay: int
    delay_events: List[DelayEvent]
    delay_by_cause: Dict[str, int]
    delay_by_party: Dict[str, int]
    recommended_extension: int
    potential_damages: float

class DelayAnalyzer:
    """Analyze construction schedule delays."""

    # Daily delay costs by project size
    DEFAULT_DAILY_COSTS = {
        "small": 5000,      # < $10M
        "medium": 15000,    # $10M - $50M
        "large": 40000,     # $50M - $200M
        "mega": 100000      # > $200M
    }

    def __init__(self, project_name: str, contract_completion: datetime):
        self.project_name = project_name
        self.contract_completion = contract_completion
        self.delay_events: Dict[str, DelayEvent] = {}
        self.schedule_versions: Dict[str, ScheduleVersion] = {}
        self.window_periods: List[WindowPeriod] = []
        self.daily_cost = self.DEFAULT_DAILY_COSTS["medium"]

    def set_daily_delay_cost(self, cost: float):
        """Set daily delay cost for damages calculation."""
        self.daily_cost = cost

    def add_schedule_version(self, version_id: str, version_type: str,
                            data_date: datetime, completion_date: datetime,
                            activities: Dict[str, Dict]) -> ScheduleVersion:
        """Add schedule version for analysis."""
        version = ScheduleVersion(
            version_id=version_id,
            version_type=version_type,
            data_date=data_date,
            completion_date=completion_date,
            activities=activities
        )
        self.schedule_versions[version_id] = version
        return version

    def add_delay_event(self, id: str, description: str,
                       cause: DelayCause, delay_type: DelayType,
                       start_date: datetime, end_date: datetime,
                       affected_activities: List[str],
                       responsible_party: str,
                       supporting_docs: List[str] = None) -> DelayEvent:
        """Add delay event for analysis."""
        event = DelayEvent(
            id=id,
            description=description,
            cause=cause,
            delay_type=delay_type,
            start_date=start_date,
            end_date=end_date,
            affected_activities=affected_activities,
            responsible_party=responsible_party,
            supporting_docs=supporting_docs or []
        )
        self.delay_events[id] = event
        return event

    def perform_as_planned_vs_as_built(self) -> Dict:
        """Perform As-Planned vs As-Built analysis."""
        baseline = self.schedule_versions.get("baseline")
        as_built = self.schedule_versions.get("as_built")

        if not baseline or not as_built:
            raise ValueError("Need baseline and as-built schedules")

        total_delay = (as_built.completion_date - baseline.completion_date).days

        # Analyze each activity
        activity_delays = []
        for act_id, baseline_act in baseline.activities.items():
            if act_id in as_built.activities:
                as_built_act = as_built.activities[act_id]

                baseline_finish = baseline_act['finish']
                actual_finish = as_built_act['finish']

                if isinstance(baseline_finish, str):
                    baseline_finish = datetime.fromisoformat(baseline_finish)
                if isinstance(actual_finish, str):
                    actual_finish = datetime.fromisoformat(actual_finish)

                delay = (actual_finish - baseline_finish).days

                if delay > 0:
                    activity_delays.append({
                        'activity_id': act_id,
                        'planned_finish': baseline_finish,
                        'actual_finish': actual_finish,
                        'delay_days': delay
                    })

        return {
            'method': 'As-Planned vs As-Built',
            'baseline_completion': baseline.completion_date,
            'actual_completion': as_built.completion_date,
            'total_delay': total_delay,
            'activity_delays': sorted(activity_delays, key=lambda x: -x['delay_days'])
        }

    def perform_time_impact_analysis(self, delay_event_id: str) -> Dict:
        """Perform Time Impact Analysis for specific delay event."""
        if delay_event_id not in self.delay_events:
            raise ValueError(f"Delay event {delay_event_id} not found")

      